Another month of construction works. Good progress again – all gyproc panels are installed – floors, walls and ceilings, joints were filled and surface finish applied. On the second floor walls were also painted with base paint. All bathrooms were water insulated. Fireplace chimney was built. All exterior doors were installed (except for the main one, since it is used a lot, and we wouldn’t like to scratch it). Sauna was measured and delivered from Keminmaa. Stairs were measured and ordered.
Of course there’s been a fair share of mistakes and disappointments.
One of the windows on the first floor cracked – looks like there’s been some hidden tension. Factory promised to send a replacement soon, hopefully it doesn’t take much time – it was one of the largest windows.
Kitchen and fitted furniture manufacturer representatives paid a visit to the construction site – double checking the measures, and we figured that pipes for the washing machine were made on the wrong wall, kitchen layout has to be modified because windows are few centimeters taller than in the plan, light switch in one bedroom will have to be moved, because it was placed behind fitted closet, and there was one pipe going through the place where fitted closets in the housekeeping room were planned.
Plumbers said that ground source heat pump doesn’t fit into the technical room and now it’ll take some space from the walk-in closet or from housekeeping room. And since floors were tiled/walls painted only in technical room, installation of the heating system is delayed.
But the project goes on despite of all small hickups – using agile methods works in construction as well as in software development.
As construction works progress, less and less materials are stored outside, but more and more garbage accumulates. With the help of two local guys all garbage was sorted according to
Three more weeks of work are behind. Good progress. House project is 63% complete according to the official statement from chief engineer.
Works inside the house continue with some hickups. Estonian construction contractor is doing excellent job, but electricians and plumbers are really weird. Now we are falling behind the schedule almost one week because of plumbers’ no-shows. Now the project manager is changed and hopefully next week all plumbing on the second floor is finished, including floor heating pipes, and roof vent pipes are installed.
Work inside the house has started as planned. After just one week of work all partition walls in the house are ready, so it is now much easier to see what it will look like when everything is finished.
Car shed progress is now visible – walls are in place, everything is ready for the roofing tiles installation. Small design changes were made, that slowed down the work a bit. Central pillar was removed after consultations with responsible engineer – it was just a decorative element and would’ve been a real problem if left in its place, since the shed is placed so that one needs to turn 90 degrees when driving into it from the road. Also we decided to prepare for the possibility of installing heating in the storage area in the future. Insulation needs to be installed for that, so I spent a few hours on Saturday carrying sacks of Paroc wool from the local store to the construction site.
Today the floors were done. 8 cm of concrete poured on the floor, levelled and covered with protective plastic. Now just waiting for it to dry.
After thermal insulation was in place, water pipes and electrical cables were installed, then steel grid was placed on top, to reinforce future concrete floors. On top of the steel grid floor heating pipes were installed. With all that in place everything is ready for 80mm thick concrete layer. It’s been a bit of a challenge to arrange all that – all parts of the work were done by different subcontractors specializing in their own areas, so a lot of synchronization was needed.
I became an employer for the first time – hired a couple of guys to build car shed. Actually that is more than a shed – there’s also place for bicycles, garbage, and two storage areas. In the end it is supposed to look like
15 cm of Styrox (thermal insulation) has been already placed on the floor when I realised that pipes for radon were not placed in the ground. Bummer. Totally forgot about it.