Good progress again on interior works. Library has been completely done, glass doors installed – they look really nice – just enough light get through the stairwell window.
Kitchen installation has been started – all cabinets are in place, wine cooler, freezer, fridge, dishwasher have been installed.
Few mistakes have been made though – forgot about wall tiles for the kitchen – need to deliver them to the site, and now a couple of electrical outlets will have to be re-done. Electrical cable for the bar shelf lights have been done in the wrong place – need to move it 40cm, so a part of the wall will have to be repainted.
Small things keep popping up – like the lights for the kitchen and bathroom walls are still needed, a light with motion detector for the garbage shed, etc.
The biggest worry is still water and sewerage – with just two weeks to go nothing has been installed or tested, and contractor didn’t return my calls on Friday.