Work inside the house has started as planned. After just one week of work all partition walls in the house are ready, so it is now much easier to see what it will look like when everything is finished.
An opening was made for easy access to the second floor while construction works are going on. Later same opening will be used to install the stairs.
Almost all ventilation pipes were installed – next week ventilation machine will be delivered. Thermal insulation between the floors and soundproofing were also almost done.
Next week work continues at full speed – electricians come over to start with the cables, pipe for the fireplace will be installed, and brick walls around the sauna and shower room will be built.
Unfortunately due to extremely bad weather installation of the roof over the car shed took longer than expected, so it will be completed most probably only next month.