Ground works are progressing quite good, despite of the small hiccup in the beginning. It is time to put the pipes into the ground. Sewer and water pipes are ordered, a plummer will come to make sure pipes are placed into the ground correctly, and another plummer from Inkoo municipality is coming to make sure connections to the municipal systems. The day and time is agreed and everybody gathers on the construction site.
But what was supposed to be a one hour job turned out to be a day of wasted time for everyone. Pipes were placed into the ground and water pipes were even connected, but sewer connection was simply impossible because of overlapping problems – as soon as the hole was dug up to get to the collector it started to immediately fill with ground water. When water pump was brought (I didn’t yet have electricity connected, so thanks to the neighbours who allowed to use their connection) and water was pumped out it was discovered that sewer connection is incorrectly made and it is not possible to connect the pipes. By that time working day was over for municipal plummer, so fixing and connection had to be postponed.